Action   13.
Regular Board of Supervisors Meeting
Meeting Date:
04/09/2013
Title:
Contract Increase for Emulsified Asphalt Products in the Amount of $700,000.
Submitted By:
Dave Seward, Procurement
Department:
Procurement
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature Required
# of ORIGINALS
Submitted for Signature:
2
NAME
of PRESENTER:
Karen Riggs
TITLE
of PRESENTER:
Interim Director Community Development
Mandated Function?:
Federal or State Mandate
Source of Mandate
or Basis for Support?:
Docket Number (If applicable):

Information

Agenda Item Text:

Approve an increase in the not to exceed dollar amount of Contract No. 10-66-HFP-04 with Western Emulsions, Inc. for CRS-2 and CRS-2P emulsified asphalt products from $1,350,000 to $2,050,000.

Background:

On July 10, 2012, The Board of Supervisors approved the renewal of Contract No. 10-66-HFP-04 in the amount of $1,350,000 for the purchase of CRS-2 and CRS-2P emulsified asphalt product for the period of August 1, 2012 through July 31, 2013. An additional amount of $700,000 is required due to unanticipated projects not included in the annual work plan to include Foothills, San Simon, Bowie, and Gleeson roads/areas as well as IGA projects bringing the total not to exceed dollar amount to $2,050,000.

Department's Next Steps (if approved):

Process a change order to the existing contract and monitor contract performance.

Impact of NOT Approving/Alternatives:

The unanticipated projects will not be completed.

To BOS Staff: Document Disposition/Follow-Up:

No action required.

Fiscal Impact

Fiscal Year:
One-time Fixed Costs? ($$$):
Ongoing Costs? ($$$):
County Match Required? ($$$):
A-87 Overhead Amt? (Co. Cost Allocation $$$):
Source of Funding?:

Fiscal Impact & Funding Sources (if known):

Community Development has budgeted for this expenditure.