Public Hearings 14.
Regular Board of Supervisors Meeting
Solid Waste
- Meeting Date:
- 07/08/2014
- Title:
- Construction and Demolition Tipping Fee Increase of $6.50 to $60.00 per ton
- Submitted By:
- Marty Haverty, Solid Waste
- Department:
- Solid Waste
Presentation:
PowerPoint
Recommendation:
Disapprove
Document Signatures:
BOS Signature Required
# of ORIGINALS
Submitted for Signature:
Submitted for Signature:
2
NAME
of PRESENTER:
of PRESENTER:
Marty Haverty
TITLE
of PRESENTER:
of PRESENTER:
Director, Solid Waste Department
Mandated Function?:
Federal or State Mandate
Source of Mandate
or Basis for Support?:
or Basis for Support?:
Docket Number (If applicable):
Information
Agenda Item Text:
Adopt Resolution 14-17, authorizing a $6.50 increase to the Solid Waste Construction and Demolition disposal rate for Fiscal Year 2014-15 from $53.50 to $60.00 per ton tipping fee effective August 8, 2014.
Background:
This proposed action to increase the user fees for customers wishing to dispose of Construction and Demolition Debris at the Urban Transfer Stations is brought before you to cover the costs of operating the system and handling that specific material. The Rate Review and Advisory Board met and voted to recommend to the Board of Supervisors that the cost to dispose of construction and demolition debris be increased by $6.50 per ton.
Department's Next Steps (if approved):
The approved item will be presented to the public for a 30 day public notice period. In addition to formal public notice, customers at each Solid Waste Facility will be informed of the upcoming fee changes, during this 30 day time span. At the end of those 30 days: August 8, 2014 the fee increase will take effect.
Impact of NOT Approving/Alternatives:
If not approved revenue will not support expenses and the department will have to seek alternative funding sources to cover Solid Waste Department shortfalls
To BOS Staff: Document Disposition/Follow-Up:
Resolution to be signed/recorded, is attached.