- Adopt Resolution 16-__ Authorizing the addition of 0.5 miles of Skyline Road to the Cochise County Maintained Road System
- Submitted By:
- Teresa Murphy, Community Development
- Department:
- Community Development
- Division:
- Right of Way
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature Required
# of ORIGINALS
Submitted for Signature:
Submitted for Signature:
5 or More
NAME
of PRESENTER:
of PRESENTER:
Karen Riggs
TITLE
of PRESENTER:
of PRESENTER:
Director
Mandated Function?:
Federal or State Mandate
Source of Mandate
or Basis for Support?:
or Basis for Support?:
ARS 28-6705
Docket Number (If applicable):
Information
Agenda Item Text:
Adopt Resolution 16-45 authorizing the addition of 0.5 miles of Skyline Road, from Calle Tortuga to Chaparral Place to the County Road Maintenance System.
Background:
The Road Drop/Add Policy was approved in 2007 and since that time a total of 9.65 miles was dropped and 7.85 miles have been added in Supervisory District 3, leaving a balance of 1.8 miles. At this time Supervisor Searle is requesting that 0.5 miles of Skyline Road be added in the Mescal area. (Please see attached map.) This segment of road is an extension of an existing County maintained road and serves several residences.
Per the Road Drop/Add Policy staff reviewed the road and reports as follows:
The drainage issue requiring gabion erosion protection would be a serious deterrent to acceptance except for Supervisor Searle’s agreement to pay the $18,800 cost. We believe this will minimize ongoing drainage maintenance costs in the future. However, the resident must understand that the maintenance level is limited to “primitive”, which will mean simple grading just a few times a year.
Drainage issues:
The road is downstream of a sizeable mis-aligned ADOT concrete box culvert that directs storm water flow under Interstate 10 and through the subject road. The directed flow from the ADOT box culvert is currently eroding the channel bank and if left unprotected will cut through the subject road beyond the existing flow path (see attached aerial image, figure 2).
This requires either 1) rebuilding the channel bank and road after every storm event or 2) constructing an erosion protected bank stabilization structure to eliminate the erosion along the bank and still maintain the clearing of sediment on the wash and road after every storm event. Under the Add/Drop program the road will be eligible for primitive maintenance that does not allow for the purchasing or laying of cement (ARS 28-6705). Therefore bank stabilization is limited to gabion structures without grouted protection. In order to allow for the installation of cement the road would need to be established as a county highway and, due to highway liability, improved to an adopted standard, (which would need to be chip seal).
The adjoining property owner has agreed to dedicate an additional spot drainage easement for dip crossing maintenance and cleaning downstream of the road.
Per the Road Drop/Add Policy staff reviewed the road and reports as follows:
- Yes, the road was open and in use prior to June 13, 1975 as evidenced by a 1973 USGS 7.5 minute Mescal Quadrangle map.
- No, there is not a minimum width of 50 feet of public right-of-way.The adjoining property owners have agreed to dedicate 30 feet to the public with an additional spot drainage easement.
- Yes, there is a minimum average width of 18 feet or more of travelway.
- Yes, the road is contiguous to another County Maintained Road.
- Yes, the road is located within the same district as a dropped road.
- Yes, the road has a minimum ADT of about 50 or more.Actual count was 115 on 12/2015.
- Yes, the road has a safe driving speed of about 35 mph under most weather conditions.
- Yes, with the exception of mesquite vegetation that can be trimmed on a maintenance basis, the road is free of hazardous encroachments.
- No, drainage issues are not minimal. Please see detailed explanation below.
- Yes, only routine environmental permits will be required.
- Yes, there are no utility conflicts.
- Yes, substandard maintenance may be in accordance with ARS 28-6705 regarding Primitive Roads, except for drainage issues as noted.
The drainage issue requiring gabion erosion protection would be a serious deterrent to acceptance except for Supervisor Searle’s agreement to pay the $18,800 cost. We believe this will minimize ongoing drainage maintenance costs in the future. However, the resident must understand that the maintenance level is limited to “primitive”, which will mean simple grading just a few times a year.
Drainage issues:
The road is downstream of a sizeable mis-aligned ADOT concrete box culvert that directs storm water flow under Interstate 10 and through the subject road. The directed flow from the ADOT box culvert is currently eroding the channel bank and if left unprotected will cut through the subject road beyond the existing flow path (see attached aerial image, figure 2).
This requires either 1) rebuilding the channel bank and road after every storm event or 2) constructing an erosion protected bank stabilization structure to eliminate the erosion along the bank and still maintain the clearing of sediment on the wash and road after every storm event. Under the Add/Drop program the road will be eligible for primitive maintenance that does not allow for the purchasing or laying of cement (ARS 28-6705). Therefore bank stabilization is limited to gabion structures without grouted protection. In order to allow for the installation of cement the road would need to be established as a county highway and, due to highway liability, improved to an adopted standard, (which would need to be chip seal).
The adjoining property owner has agreed to dedicate an additional spot drainage easement for dip crossing maintenance and cleaning downstream of the road.
Department's Next Steps (if approved):
If approved, the road segment will be brought into the maintenance system as a Primitive Road.
Impact of NOT Approving/Alternatives:
Should the item not be approved the road segment will not be brought into the Road Maintenance System.
To BOS Staff: Document Disposition/Follow-Up:
Please return the original deeds/dedications and copy of recorded Resolution to Teresa Murphy, H&F Div
Fiscal Impact
Attachments
- Resolution
- Executive Summary
- Drainage Easement-Adkins
- Deed of Dedication
- Executive Summary Map
- Deed of Dedication
- Deed of Dedication
- Deed of Dedication
- Location Map