Action   15.
Regular Board of Supervisors Meeting
Fleet & Heavy Fleet
Meeting Date:
09/28/2021
Title:
Approval of Light Fleet vehicle replacements.
Submitted By:
Marty Haverty, Public Works
Department:
Public Works
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature NOT Required
# of ORIGINALS
Submitted for Signature:
0
NAME
of PRESENTER:
Marty Haverty
TITLE
of PRESENTER:
Director, Public Works Department
Mandated Function?:
Not Mandated
Source of Mandate
or Basis for Support?:
Docket Number (If applicable):

Information

Agenda Item Text:

Approve purchase of replacement vehicles for the Light Fleet Division in the total amount of $523,641.76, as appropriated in the Fiscal Year 2021-22 budget.

Background:

The Light Fleet Division of Public Works manages the capital replacement account to ensure the timely rotation of vehicles that have reached the end of their useful life from the fleet.  Each department within the county contributes to the replacement fund on a per mile cost basis which differs depending upon the type and cost of the vehicle to be replaced.  The program is set up and administered to ensure that we always have the available replacement funds in a timely manner.  The proposed replacement vehicles have been budgeted in this year's budget, which was already approved by the BOS.  

Vehicles to be replaced are listed below:
DEPT # VEHICLE # Model Yrly use Life Miles Repl Miles Unit Cost Upfits
IT 00001-0274 08 K-2500 Ext Cab 20,150 160,700 180,000  $    39,661.63  $     1,000.00
Dev Se 00001-0169 2011 Colorado 2WD 24,653 171,105 180,000  $    24,830.48  $     1,000.00
CCSO 00001-0348 2012 K-1500 Crew 14,387 162,559 180,000  $    38,145.10  $     4,084.95
CCSO 00001-0614 2015 K-2500 Crew 28,274 138,042 180,000  $    38,853.59  $     4,084.95
CCSO 00001-0615 2015 K-2500 Crew 31,083 140,269 180,000  $    38,853.59  $     4,084.95
CCSO 00001-0650 2015 K-2500 Crew 27,252 154,343 180,000  $    38,837.23  $     8,174.79
CCSO 00001-660 2015 K-1500 Crew 28,060 139,533 160,000  $    35,382.78  $     8,174.79
CCSO 00001-0683 2014 Tahoe 2WD 21,978 131,158 160,000  $    39,106.58  $  10,564.00
CCSO 00001-0696 2014 Tahoe 2WD 34,914 129,437 160,000  $    39,106.58  $  10,564.00
CCSO 00001-0697 2014 Tahoe 2WD 23,989 139,793 160,000  $    39,106.58  $  10,564.00
CCSO 00001-0698 2014 Tahoe 2WD 26,247 142,525 160,000  $    39,106.58  $  10,564.00
Lib 00001-0041 2015 Express Van 36,826 166,154 180,000  $    39,791.04  
Sub Total           $450,781.76 $72,860.00
Total             $523,641.76

The second cost column which totals $72,860 is for "upfits" to these newly acquired vehicles to ensure all CCSO vehicles are ready when they arrive in Bisbee. 

Department's Next Steps (if approved):

With approval, the Light Fleet Division will generate a Purchase Order and work with Procurement to complete the purchase.

Impact of NOT Approving/Alternatives:

The auto industry is having issues with the supply chain at this time and delays for delivery are expected even if approved.  This creates an issue when replacing CCSO (pursuit) vehicles that are close to the standard of 160,000 miles for end of life.  If delays are apparent we will decrease the service intervals for those vehicles so that we can provide preventative maintenance on them more frequently.
 
If not approved the county will incur costs in repair and maintenance that far exceed the cost of a new vehicle, in addition to increasing risk to all with an aging CCSO patrol fleet.

To BOS Staff: Document Disposition/Follow-Up:

Public Works staff is only seeking approval to expend funds that have been approved in the budget process.

Fiscal Impact

Fiscal Year:
2022
One-time Fixed Costs? ($$$):
$523,641.76
Ongoing Costs? ($$$):
N/C to Current
County Match Required? ($$$):
No
A-87 Overhead Amt? (Co. Cost Allocation $$$):
N/A
Source of Funding?:
See Below

Fiscal Impact & Funding Sources (if known):

This purchase is budgeted and will be expended from 109-160-9-454.100 (Motor Vehicles Replacement) Current Account Balance $725,000.
No change to ongoing costs since these are replacement vehicles.

Attachments

No file(s) attached.