Action   13.
Regular Board of Supervisors Meeting
Meeting Date:
04/24/2012
Title:
Approval of Change Orders - Douglas Government Center Construction Project
Submitted By:
Dave Seward, Procurement
Department:
Procurement
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature NOT Required
# of ORIGINALS
Submitted for Signature:
0
NAME
of PRESENTER:
Dave Seward
TITLE
of PRESENTER:
Procurement Director
Mandated Function?:
Federal or State Mandate
Source of Mandate
or Basis for Support?:
Docket Number (If applicable):

Information

Agenda Item Text:

Approve Change Order Requests 26, 42, 44, 47, 48, 49, 50, 52, 55, 57, 58, 59, 60, 61, 62, 63, and 64 for Concord General Contracting in the amount of $79,650.09 for the Douglas Government Center Construction Project.

Background:

The original contract amount with Concord General Contracting was $3,849,000. Previously approved change orders with Concord total $175,336. The contingency amount for this project is $200,000. A brief explanation for these change orders is attached. Substantial completion for this project is April 23, 2012. There are three outstanding change orders that total approximately $4,000 that are currently being negotiated.

The Architect, Construction Manager, and Project Manager have reviewed and approved these change orders. The total amount requested by Concord was negotiated from $92,558.09 to the amount of $79,650.09 during the change order review process. Change orders of $30,000 or more require Board of Supervisors approval in accordance with the procurement policy.

Department's Next Steps (if approved):

Process a contract amendment to Concord General Contracting.

Impact of NOT Approving/Alternatives:

The work required by these change orders will not be done.

To BOS Staff: Document Disposition/Follow-Up:

No action required.

Fiscal Impact

Fiscal Year:
One-time Fixed Costs? ($$$):
Ongoing Costs? ($$$):
County Match Required? ($$$):
A-87 Overhead Amt? (Co. Cost Allocation $$$):
Source of Funding?:

Fiscal Impact & Funding Sources (if known):

Budgeted in the construction contingency fund.