- Meeting Date:
- 09/01/2015
- From:
- Thomas Bolyen, Water Production Manager
Information
TITLE:
RECOMMENDED ACTION:
1) Approve construction contract with Commonwealth Electric Company for $506,500.00, and a contract time of sixty (60) calendar days.
2) Authorize change order authority to the City Manager in the amount of $50,650.00 (10% of contract amount).
3) Authorize City Manager to execute the necessary documents.
Executive Summary:
Financial Impact:
This project has been funded through the Utilities Fund’s Operations and Maintenance Budget. Funds are budgeted in account 202-08-301-1014-0-4402 $125,000.00 and account 202-08-301-1020-0-4405 $375,000.00. Remainder of the needed funds to be provided by the Water Production Operating Budget.
Connection to Council Goal and/or Regional Plan:
2) Ensure Flagstaff has a long-term water supply for current and future needs
3) Provide sustainable and equitable public facilities, services, and infrastructure systems in an efficient and effective manner to serve all population areas and demographics
REGIONAL PLAN GOALS:
Chapter VI, WR.2.1, Develop and adopt an integrated water master plan that addresses water resources, water production and its distribution, wastewater collection and its treatment, and reclaimed water treatment and its distribution. Chapter VI, Policy WR.2.2, maintain and develop facilities to provide reliable, safe, and cost-effective water, wastewater and reclaimed water services
Has There Been Previous Council Decision on This:
Options and Alternatives:
2) Do not award this contract and request staff to re-bid the project.
3) Do not approve this request increasing the city’s risk during an emergency or sustained loss of power for insufficient fire protection.
Background/History:
Staff issued a solicitation for construction bids, and was advertised on June 14 and June 21, 2015. Four bids were received by the opening date of June 29, 2015, and Commonwealth Electric Company was determined to be the lowest responsive responsible bidder. A tabulation of bids received is summarized below in the Expanded Financial Considerations.
Key Considerations:
The Flagstaff water system is very robust in its sources and facilities which are a definite advantage for problems internal to the city’s electrical grid, but all the water services for the City of Flagstaff rely on a single source of power coming up the mountain. The allocation of electricity from another provider or an additional mountain source of electrical power is currently unavailable. Our only power source provided by APS is from a single substation susceptible to mechanical failure, lightning, wild fire, and statewide emergency. During heavy monsoons we are constantly challenged by interruptions in our power supply. A sustained long term power outage or actual emergency that may impact the power distribution grid leaves the city vulnerable limiting our ability to pump or provide any reliable water and storage supplies will become depleted.
Expanded Financial Considerations:
Tabulation of Bids:
Contractor Bid
Commonwealth Electric Co. $506,500.00
LE Ludvik Electric $509,315.00
N.J. Shaum & Son, Inc. $537,904.00
TSG Constructors, LLC $587,000.00