STAFF RECOMMENDED ACTION:
- Approve the construction contract with Kinney Construction, LLC in the amount of $1,325,256.00 and a contract duration of 175 calendar days;
- Approve a contract allowance of $66,262.80, which is 5% of the lowest responsive bid;
- Approve Change Order Authority to the City Manager in the amount of $132,525.60 which is 10% of the lowest responsive bid;
- Authorize the City Manager to execute the necessary documents.
Executive Summary:
The Sheep Crossing Trail is a planned Flagstaff Urban Trails System (FUTS) trail, approximately 0.8 miles in length, 10 feet in width, which will connect the Ponderosa FUTS Trail along the west side of Pulliam Drive with the Sinclair Wash FUTS Trail in Fort Tuthill County Park. This multi-use, non-motorized, aggregate mix trail will allow users the opportunity to navigate under Interstate 17, connecting existing trails on the east and west sides of the Interstate, just north of the John Wesley Powell Boulevard and Interstate 17 Interchange. This trail segment is also part of the ultimate alignment of the Flagstaff Loop Trail, a 44-mile system of FUTS, County, and US Forest Service trails that circumnavigate the community and provide a world-class recreational opportunity in proximity to the city.
Financial Impact:
Policy Impact:
Connection to Council Goal, Regional Plan, CAAP, and/or Strategic Plan:
- Deliver quality community assets and continue to advocate and implement a highly performing multi-modal transportation system.
Council Goal || Environmental and Natural Resources
- Actively manage and protect all environmental and natural resources.
Regional Plan Goal || Environmental Planning & Conservation
- Reduce Greenhouse Gas Emissions (E&C.2)
Regional Plan Goal || Community Character
- Reflect and respect the region’s natural setting and dramatic views in the built environment (CC.1)
Regional Plan Goal || Transportation
- Improve mobility and access throughout the region. (T.1)
- Improve transportation safety and efficiency for all modes. (T.2)
- Increase the availability and use of pedestrian infrastructure, including FUTS, as a critical element of a safe and livable community. (T.5)
- Provide for bicycling as a safe and efficient means of transportation and recreation. (T.6)
Flagstaff Strategic Plan || Work in Partnership to Enhance a Safe and Livable Community
- Foster a safe, healthy, equitable and accessible community.
Has There Been Previous Council Decision on This:
Options and Alternatives:
- Approve the award for the construction contract as recommended. Approval will allow work on the project to move forward.
- Reject all bids. This action would delay the project.
- If rejection occurs, possible options include:
- Re-advertise the project and open new bids or
- Suspend or cancel the project
- If rejection occurs, possible options include:
Background and History:
For years a solution has been sought for trail connectivity from an east-to-west transect traversing Interstate 17, south of Interstate 40. An investigation began to utilize the dual concrete box tunnels located under Interstate 17. After four years of working with project stakeholders, a design engineer, and numerous sub-consultants, a multi-agency effort has paved a path forward for this project to be constructed. This unique partnership is well represented by the trail crossing four jurisdictions: federal (US Forest Service), state (Arizona Department of Transportation), county (Coconino County), and municipality (City of Flagstaff).
Key Considerations:
Company Bid
Engineer’s Estimate $1,230,119.00
Kinney Construction, LLC $1,325,256.00
Mountain High Excavating, LLC $1,348,764.00
Standard Construction, Inc. $1,380,524.00
MD Merrett, Inc. $1,596,374.16
Community Involvement:
The Sheep Crossing FUTS Trail will act as a critical connection corridor for multi-use, non-motorized users to have trail connectivity under Interstate 17 from the Ponderosa FUTS Trail (Ponderosa Trails Subdivision) to the Sinclair Wash FUTS Trail at Fort Tuthill County Park.
This trail segment is also part of ultimate alignment of the Flagstaff Loop Trail, a 44-mile system of FUTS, County, and US Forest Service trails that circumnavigate the community and provide a world-class recreational opportunity in proximity to Flagstaff.