5.A.
Heritage Preservation Commission
- Meeting Date:
- 09/15/2021
- From:
- Mark Reavis, Heritage Preservation Officer and Neighborhood Planner
TITLE:
Monte Vista Hotel - Phase 3 Addition
PROPERTY INFORMATION:
Address: 100 N San Francisco St
Assessor's Parcel Number: 101-19-005
Property Owner: Craven Enterprises LLC
Applicant: Karl Eberhard
City Staff: Mark Reavis, Heritage Preservation Officer
Assessor's Parcel Number: 101-19-005
Property Owner: Craven Enterprises LLC
Applicant: Karl Eberhard
City Staff: Mark Reavis, Heritage Preservation Officer
REQUESTED ACTION:
Approve a Certificate of Appropriateness for Phase 3 improvements to an existing historic Monte Vista Hotel on the east of the hotel’s secondary facade. The review includes a street facing parking entry with a patio area over a portion of the parking. The project is located within the Downtown Overlay Zone.
RECOMMENDED ACTION:
Approve a Certificate of Appropriateness for Phase 3 of the Monte Vista Hotel Improvements with a condition that the Heritage Preservation Office be provided an acceptable paint chip with color and LRV specifications for the stucco of Phase 3 based on the feedback provided by the Heritage Preservation Commission.
Alternative Actions:
- The Commission could approve a Certificate of Appropriateness for the submitted architectural package. This includes the HPO recommended adjustments of stucco colors and Light Reflective Value (LRV) that is a balance between Downtown Overlay design criteria and Flagstaff’s typical limitation that requires an LRV of 50% or less. The Commission should note the required findings in the HPO Staff Report and whether the situation in this case would be applicable to other similar properties in the district.
- The Commission could request modifications to the proposal and include them as conditions of approval – or –
- Continue the HPC review to a date certain and ask the applicant to come back with a modified proposal that meets those conditions.
Has There Been Previous Commission Decision on This:
The HPC has has reviewed the Master Plan and Phase 2 work on the Monte Vista Hotel