9.C.
City Council Meeting - FINAL
- Meeting Date:
- 01/15/2013
- From:
- Erin Young, Water Resources Manager
Information
TITLE:
Consideration and Approval of Amendment to Contract: Amendment to add Water Infrastructure Finance Authority (WIFA) Federal Loan Provisions to Contract.
RECOMMENDED ACTION:
Approve Contract Amendment One for the Red Gap Ranch Pipeline Alignment Feasibility Study with Jacobs Engineering Group, Inc.
Policy Decision or Reason for Action:
Upon receipt of a letter to the City from WIFA, Staff became aware that the loan dollars were coming from the Capitalization Grants for Drinking Water State Revolving Funds. Staff realized that the original contract with Jacobs Engineering Group, Inc. did not include the necessary Federal WIFA loan provisions required to be recognized by the WIFA Loan Program. The Grants Manager has worked with Jacobs Engineering Group, Inc. to include the WIFA provisions at no additional cost to the City, which will bring the contract into compliance and recognized by the WIFA Loan Program.
Subsidiary Decisions Points: Acceptance of Contract Amendment One is necessary before the City can be refunded by WIFA loan for work already completed under the contract.
Subsidiary Decisions Points: Acceptance of Contract Amendment One is necessary before the City can be refunded by WIFA loan for work already completed under the contract.
Financial Impact:
There is no cost associated with amending the contract with Jacobs Engineering Group, Inc.
Connection to Council Goal:
Effective governance.
Has There Been Previous Council Decision on This:
No.
Options and Alternatives
Staff recommends Council approve the contract amendment so that Finance can receive funds from the WIFA loan to cover the contract amount of $1,999,425 is already been paid by the City to Jacobs Engineering Group, Inc. Should Council not approve the contract amendment, the City will be fully responsible for covering the contract amount and will not receive the loan dollars from WIFA.
Community Benefits and Considerations:
Inform
Council Action:
Approved by CC on 1/15/2013 - EAB
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing Director | Erin Young | 12/20/2012 05:33 PM |
| Grants, Contracts & Emergency Mgmt. | Stacey Brechler-Knaggs | 12/21/2012 10:21 AM |
| Purchasing Director | rcompau | 12/21/2012 02:47 PM |
| Legal Assistant | Vicki Baker | 01/02/2013 04:42 PM |
- Form Started By:
- Erin Young
- Started On:
- 12/20/2012 05:19 PM
- Final Approval Date:
- 01/11/2013