AI - 100366
3.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 08/19/2025
- Submitted For:
- Yvette Barrera
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No.1, reflecting 25 additional calendar days for the project ''Southwest Weslaco Ph III-A IBWC Structure 105AL -2018 Bond Referendum Project No. 35'', Contract No. (C-HCDD1-24-055-11-12), with Mor-Wil, LLC, as recommended by Project Engineer, S2 Engineering, PLLC and approved by District General Manager, Raul E. Sesin, PE, CFM.
BACKGROUND
End Date for change order 1 - September 21, 2025
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 08/15/2025 02:33 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 08/11/2025 11:05 AM
- Final Approval Date:
- 08/15/2025