CAPTION
Ratification of approved and fully executed Change Order No. 1, reflecting an increase in the amount of $12,650.61 and an additional 21 construction calendar days for the project ''Pharr - McAllen Lateral West - 2023 Bond Referendum Project No. 9'', Contract No. C-HCDD1-25-013-04-15, with Construx Enterprises, LLC, as recommended by Project Engineer Izaguirre Engineering Group, LLC, and approved by District General Manager, Raul Sesin, PE, CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/17/2025 03:44 PM |
- Form Started By:
- Justin Silva
- Started On:
- 09/16/2025 02:17 PM
- Final Approval Date:
- 09/17/2025