CAPTION

Requesting approval of Supplemental Agreement No. 1 to Work Authorization No. 7 for current contract (contract C-07-358-09-04 approved by CC on 05/13/08) with R. Gutierrez Engineering for the South Tower Park to reflect a $4,000.00 increase to the total project estimated cost, bringing the total estimated project cost to $12,000.00. C-07-358-09-04

BACKGROUND

PO # 603743

Fiscal Impact

FISCAL YEAR:
2008
ACCT. #:
8-1212-452-00-122-008-0-739
FUNDS AVAILABLE Y/N?:
Pending
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO 603743 has a balance of $8,000.00 as of 7/25/08.  A PO increase will be needed in the amount of $4,000.00 to bring the aforementioned PO amount to the total of $12,000.00.  Funding is available in the account for the required PO increase.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/22/2008 04:00 PM
Budget and Management Veronica Lopez 07/25/2008 08:20 AM
Auditor's Office 07/25/2008 09:33 AM
Form Started By:
Rocio Villarreal
Started On:
07/22/2008 11:49 AM
Final Approval Date:
07/25/2008