Requesting approval of Application for Payment No. 7 in the amount of $112,252.99 for the Pct. 2 Recreational Trails Connectivity Project - Mission Segment 1 (ARPA-21-122-040) submitted by the contractor, Urbe 21 Design & Construction, LLC (Contract C-25-0170-05-13) and reviewed by the Project Manager, Stanley Ramos.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2026
- ACCT. #:
- 1301-52-122-000-0000-507400
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding is available through PO#900388 in the amount of $823,832.94 as of 02/10/26. Payment will be issued from the due from Mission Account for their committed ICA contributionAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 06/02/2026 01:06 PM |
| Budget and Management | Veronica Ortiz | 06/02/2026 01:15 PM |
| Final Approval | Monica Salinas | 06/03/2026 04:55 PM |
- Form Started By:
- Lupita Garza
- Started On:
- 05/20/2026 10:47 AM
- Final Approval Date: