La Joya Water Suppy Corp.:
1. The contractor proposes to bore & install a 16" PVC casing for a 8" PVC waterline across La Homa Rd. The bore is located 35.0' North of Calle La Camellia Rd.
2. The contractor proposed to bore & install a 16" PVC casing for a 8" PVC waterline across mile 4 Rd. Then the 8" PVC waterline will run North for 580.0' being 5.0' west of the east R.O.W. line of Texan Rd to the proposed subdivision.
North Alamo Water Supply Corp.:
1. The contractor proposes to install a 8" PVC sanitary sewer line along the north side of mile 17 1/2 Rd. The 8" PVC sanitary sewer line will begin 780.0' east of north 3rd St. And then run east 185.0' being 5.0' south of the north ROW line of mile 17 1/2 Rd.
2. Approximately 1,350' going south on private easement from the centerline of Sioux Rd and Hutto Rd on the west side and 531' going south from last meter crossing canal and Drainage Ditch- Line Ext.- Big Valley Auto Auction- NAWSC proposes to install a 6" waterline w/12" Steel Casing- 3/4" service connection.
Sharyland Water Supply Corporation:
1. A 1" PVC waterline to be encased within a 2" PVC casing crossing to be located approximately 431 ft. west of the intersection of Mayberry Rd and Mile 8 Rd.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Lopez | 08/20/2008 04:08 PM |
| Auditor's Office | lfong | 08/21/2008 02:33 PM |
| Court Administrator | Monica Salinas | 08/22/2008 04:49 PM |
- Form Started By:
- Saul Garcia
- Started On:
- 08/18/2008 01:52 PM
- Final Approval Date:
- 08/22/2008