Presentation for discussion, consideration, and approval corrected the following work authorizations between Hidalgo County & L & G Engineering Labratory:
a. Work Authorization No 1 with the corrected proposed fee of $1,026.68 and not $2,285.40 for Bernal Subd
b. Work Authorization No 2 with the corrected proposed fee of $1,986.11 and not $2,491.29 for Highland Subd and not as previously approved as La Palma Subd
c. Work Authorization No 3 with the corrected proposed fee of $1,030.55 and not $2,285.40 for Chapa 3
d. Work Authorization No 4 with the corrected proposed fee of $1,026.68 and not $2,636.65 for La Palma Subd. and not as previously approved as Highland Subd.
including the acceptance and substitution of all the corrected supporting documentation.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1311-431-00-121-105-1-339
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Amount available for req #137981 $1,310.60 as of 8-29-08 for L & G Engineering, LLC for Bernal S/D.- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1311-431-00-121-318-1-339
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Amount available in req #137979 $1,999.16 as of 8-29-08 for L & G Engineering, LLC for High Land.- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1311-431-00-121-150-1-339
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available Balance as of 8-29-08 $700.00; Amount available in req #136005 $336.84 as of 8-29-08 for L & G Engineering, LLC for Chapa III.- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1311-431-00-121-391-0-339
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Amount available in req #135981 $3,038.30 as of 8-29-08 for L & G Engineering, LLC for La Palma S/D.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 08/28/2008 05:33 PM |
| Budget and Management | Veronica Lopez | 08/29/2008 07:48 AM |
| Auditor's Office | 08/29/2008 05:55 PM |
- Form Started By:
- lmoya
- Started On:
- 08/28/2008 04:50 PM
- Final Approval Date:
- 08/29/2008