CAPTION
A. Request approval of Change Order No. 4 on the Contract with Ballenger Construction Company for the Construction of Levee DHS Segment 0-5. Subject to Department of Homeland Security (DHS) concurrence.
B. Request approval of Change Order No. 4 and No. 5 on the Contract with SER Construction Partners, LTD for the Construction of Levee DHS Segment 0-7. Subject to Department of Homeland Security (DHS) concurrence.
C. Request approval of Change Order No. 1, No. 2 and No. 3 on the Contract with Zachary Construction for the Construction of Levee DHS Segment 0-8. Subject to Department of Homeland Security (DHS) concurrence.
D. Request approval of Change Order No. 1, No. 2 and No. 3 on the Contract with William Brothers Construction for the Construction of Levee DHS Segment 0-9. Subject to Department of Homeland Security (DHS) concurrence
E. Request approval of Change Order No. 1 and No. 2 on the Contract with William Brothers Construction for the Construction of Levee DHS Segment 0-10. Subject to Department of Homeland Security (DHS) concurrence
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Dina Trevino | 09/25/2008 01:40 PM |
| Court Administrator | Alejandro Garcia | 09/25/2008 02:48 PM |
- Form Started By:
- mluna
- Started On:
- 09/11/2008 01:14 PM
- Final Approval Date: