AI - 12124
6.
DRAINAGE DISTRICT
- Meeting Date:
- 11/18/2008
- Submitted For:
- Lora Briones
- Submitted By:
- Minerva Luna, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
A. Request approval of Payment Request No. 4 to Ballenger Construction Company for the Construction of Levee DHS Segment 0-5 (1.76 miles).
B. Request approval of Payment Request No. 1 to Ballenger Construction Company for the Construction of Levee DHS Segment 0-6A (2.59 miles).
C. Request approval to process manual checks for the above mentioned projects to Ballenger Construction Company pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
D. Request approval of Payment Request No. 1 to SER Construction Partners, LTD. for the Construction of Levee DHS Segment 0-6B & 0-6C (1.38 miles).
E. Request approval of Payment Request No. 3 to SER Construction Partners, LTD. for the Construction of Levee DHS Segment 0-7 (0.90 miles).
F. Request approval to process manual checks for the above mentioned projects to SER Construction Partners, LTD. pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
G. Request approval of Payment Request No. 1 to Zachry Construction Corporation for the Construction of Levee DHS Segment 0-8 (3.31 miles).
H. Request approval to process manual check to Zachry Construction Corporation pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
I. Request approval of Payment Request No. 1 to McAllen Construction, Inc. for the Construction of Levee DHS Segment 0-9 PH II (1.75 miles).
J. Request approval to process manual check to McAllen Construction, Inc. pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
K. Request approval of Payment Request No. 3 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-9 PH I (2.12 miles).
L. Request approval of Payment Request No. 3 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-10 (2.33 miles).
M. Request approval to process man checks to Williams Brothers Construction Company, Inc. pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
N. Request approval of Payment Request No. 3 to Longhorn Excavators, Inc. for the Construction of the Mission Levee Improvements Project Inspiration Rd to Abram Rd.
O. Request approval to process manual check to Longhorn Excavators, Inc. pending the completion of the auditing process.
B. Request approval of Payment Request No. 1 to Ballenger Construction Company for the Construction of Levee DHS Segment 0-6A (2.59 miles).
C. Request approval to process manual checks for the above mentioned projects to Ballenger Construction Company pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
D. Request approval of Payment Request No. 1 to SER Construction Partners, LTD. for the Construction of Levee DHS Segment 0-6B & 0-6C (1.38 miles).
E. Request approval of Payment Request No. 3 to SER Construction Partners, LTD. for the Construction of Levee DHS Segment 0-7 (0.90 miles).
F. Request approval to process manual checks for the above mentioned projects to SER Construction Partners, LTD. pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
G. Request approval of Payment Request No. 1 to Zachry Construction Corporation for the Construction of Levee DHS Segment 0-8 (3.31 miles).
H. Request approval to process manual check to Zachry Construction Corporation pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
I. Request approval of Payment Request No. 1 to McAllen Construction, Inc. for the Construction of Levee DHS Segment 0-9 PH II (1.75 miles).
J. Request approval to process manual check to McAllen Construction, Inc. pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
K. Request approval of Payment Request No. 3 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-9 PH I (2.12 miles).
L. Request approval of Payment Request No. 3 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-10 (2.33 miles).
M. Request approval to process man checks to Williams Brothers Construction Company, Inc. pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
N. Request approval of Payment Request No. 3 to Longhorn Excavators, Inc. for the Construction of the Mission Levee Improvements Project Inspiration Rd to Abram Rd.
O. Request approval to process manual check to Longhorn Excavators, Inc. pending the completion of the auditing process.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Lopez | 11/13/2008 02:37 PM |
- Form Started By:
- mluna
- Started On:
- 11/05/2008 11:19 AM
- Final Approval Date:
- 11/13/2008