CAPTION
Presentation for discussion, consideration and applicable action realted to the "As Built drawings of the existing Couthouse to include Annexes and the surrounding Parking Areas & Sidewalks Project" including, but not limited to, the following options and recommendations:
A. Proceed with completing the current on-going process of selection of the architect and continue negotiations with the number one-ranked firm of ERO International, Inc. by utilizing the;
a) AIA Document B141-1997-Standard Form of Agreement Between Owner and Architect using Hidalgo County's form; or,
b) AIA Document B141-1997-Standard Form of Agreement Between Owner and Architect using McAllen ISD's form (as requested by architect ERO International, Inc.); or, in the alternative;
B. Cancel the project so as to determine the final costs, construction timelines including occupancy asssociated with the current renovations to the former Administration Building located at 100 E. Cano, Edinburg, Texas; and, if approved;
C. Proceed to send notice to the architect firm of ERO International, Inc. of the County's cancellation of the project and cease negotiations.
A. Proceed with completing the current on-going process of selection of the architect and continue negotiations with the number one-ranked firm of ERO International, Inc. by utilizing the;
a) AIA Document B141-1997-Standard Form of Agreement Between Owner and Architect using Hidalgo County's form; or,
b) AIA Document B141-1997-Standard Form of Agreement Between Owner and Architect using McAllen ISD's form (as requested by architect ERO International, Inc.); or, in the alternative;
B. Cancel the project so as to determine the final costs, construction timelines including occupancy asssociated with the current renovations to the former Administration Building located at 100 E. Cano, Edinburg, Texas; and, if approved;
C. Proceed to send notice to the architect firm of ERO International, Inc. of the County's cancellation of the project and cease negotiations.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding source to be identified once contract negotiations are finalized with awarded firm and final contract is ready to be executed.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/07/2008 04:11 PM |
| Budget and Management | Veronica Lopez | 11/07/2008 04:17 PM |
| Auditor's Office | 11/07/2008 04:48 PM |
- Form Started By:
- msalazar
- Started On:
- 11/05/2008 11:57 AM
- Final Approval Date:
- 11/07/2008