CAPTION
A. Request approval to Rescind court action on November 18, 2008 Item 6.L. on Pay Request #3 to Williams Brothers Construction Company, Inc.
B. Request approval of Payment Request No. 3 to Williams Brothers Construction Company, Inc. for the Construction of Levee DHS Segment 0-10 (2.33 miles).
C. Request approval to process manual check to Williams Brothers Construction Company, Inc. pending approval from County Auditor and pending the electronic transfer of funds from Department of Homeland Security (DHS).
D. Request approval of clarification of Change Order No. 2, No. 3, No. 4 and No. 5 for DHS Levee Segment 0-9 Phase I; Contractor Williams Brothers Construction Company, Inc. Clarification is on the supporting documentation that was provided with change orders.
E. Request approval of clarification of Change Order No. 2, and No. 4 for DHS Levee Segment 0-10; Contractor Williams Brothers Construction Company, Inc. Clarification is on the supporting documentation that was provided with change orders.
BACKGROUND
Fiscal Impact
Attachments
- Change order #2 0-10
- change order #4 0-10
- Change order #4 0-09
- Change Order #5 0-09
- Change Order #3 0-09
- Change Order #2 0-10
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Lopez | 12/05/2008 03:58 PM |
| Final Approval | Alejandro Garcia | 12/05/2008 04:21 PM |
- Form Started By:
- mluna
- Started On:
- 12/05/2008 01:28 PM
- Final Approval Date:
- 12/05/2008