AI- 12876
9.C.
CC REGULAR
- Meeting Date:
- 12/23/2008
- Submitted By:
- Estella Webber, URBAN COUNTY
- Department:
- URBAN COUNTY
Information
CAPTION
The Urban County Program requests approval of Change Order No.2 on construction contract with Joe Williamson Construction Company, Inc. to increase contract in the amount of $79,873.10, utilizing City of Alamo general funds.
BACKGROUND
The Urban County Program requests approval of Change Order No. 2 which was presented by the City of Alamo to the existing contract in the amount of $814,546.00 for the construction of a new fire station. Hidalgo County Commissioner’s Court approved change order No. 1 on December 16, 2008. The City of Alamo has requested additional work to be performed by the contractor to equal an increase of $79,873.10 for the purchase and installation of a 150kw emergency power generator for the new fire station.
Approved Contract Amount: $ 814,546.00
Change Order No. 2 (Increase) $ 79,873.10 (City of Alamo Funds)
Approved Contract Amount: $ 814,546.00
Change Order No. 2 (Increase) $ 79,873.10 (City of Alamo Funds)
Fiscal Impact
- FISCAL YEAR:
- 2008
- ACCT. #:
- N/A
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
The Change Order is for the purchase/installation of a 150kw emergency power generator for the new fire station and will be paid with non-CDBG funds.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Lopez | 12/17/2008 07:47 AM |
| Auditor's Office | Alejandro Garcia | 12/19/2008 05:14 PM |
- Form Started By:
- ewebber
- Started On:
- 12/16/2008 03:21 PM
- Final Approval Date:
- 12/19/2008