Drainage Improvement Project (1339):
Presentation for consideration, discussion, and approval of Work Authorization #2 (Supplemental Agreement No. 1) in the amount of $ 62,900.00, bringing the total cost to $548,100.00 with Quintanilla, Headley & Associates, Inc. to provide engineering services to Hidalgo County Precinct No. 4 in connection with Contract No. C-08-477-12-09 for "San Carlos Drainage Improvements Project"
BACKGROUND
WA#2-SA#1-QHA-C-08-477-12-09 From $485,200 to $ 548,100
Fiscal Impact
- FISCAL YEAR:
- 2009
- ACCT. #:
- 9-1339-431-00-124-0XX-0-733
- FUNDS AVAILABLE Y/N?:
- Pending
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding pending approval of an interdepartmental transfer (AI#15331 5/12/09).Program Pond Amount
038 Aguilar 6,800
039 Fike 11,900
048 Dikerson 40,800
060 Guerra 3,400
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 05/07/2009 02:00 PM |
| Budget and Management | Veronica Lopez | 05/07/2009 02:13 PM |
| Auditor's Office | 05/08/2009 05:26 PM |
- Form Started By:
- Letty Saenz
- Started On:
- 05/06/2009 04:02 PM
- Final Approval Date:
- 05/08/2009