Presentation for consideration, discussion, acceptance, and approval of Work Authorization No. 13 in the estimated amount of $23,857.00 for provision of engineering services in connection with additional paving and drainage work for Border Colonia Access Program (BCAP) El Charro Subdivision with R. Gutierrez Engineering through contract No. C-08-381-09-16.

BACKGROUND

BCAP Project included 0.7 miles of street improvements and the additional work is for 0.37 miles of streets. The streets included in this work are Kennedy Street, Toupi Drive and Toultec Drive.

Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1202-431-00-122-006-0-731 & 733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funding available as of 05/06/2009 on the following codes:

731---->$85,566.76
733---->$19,680.25

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 05/07/2009 02:26 PM
Budget and Management Veronica Lopez 05/07/2009 03:13 PM
Auditor's Office bmorales 05/08/2009 04:40 PM
Form Started By:
ycisneros
Started On:
05/06/2009 05:47 PM
Final Approval Date:
05/08/2009