AI- 16376
21.C.1.
CC REGULAR
Meeting Date:
07/14/2009
Submitted For:
Marty Salazar
Submitted By:
Moises Salazar, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

a. Requesting approval of Change Order No. 1 (Increase of Contract Time) in connection with Precinct No. 2 -"South Tower CRC/Park Pending Construction Items" from contracted vendor, CAS Companies, LP, and as recommended by project architect, V-A Architecture, with authority for County Judge or Court member to execute document. 

b. Requesting approval of "Certificate of Substantial Completion" with CAS Companies, LP, reflecting the substantial completion date of July14, 2009 for Precinct No. 2 -"South Tower CRC/Park Pending Construction Items" P.O. 614127. 

BACKGROUND

See Attached AIA Documents:
G701-2001 -Change Order.
G704-2000 -Certificate of Substantial completion. 

Fiscal Impact

FISCAL YEAR:
ACCT. #:
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

No fiscal impact

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/10/2009 10:14 AM
Budget and Management Erika Zamora 07/10/2009 11:46 AM
Auditor's Office 07/10/2009 05:07 PM
Form Started By:
moysalazar
Started On:
07/07/2009 04:23 PM
Final Approval Date:
07/10/2009