AI- 16428
21.F.1.
CC REGULAR
Meeting Date:
07/14/2009
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

Information

CAPTION

Approval of Change Order #1 with contractor Valley Paving, Inc. for Dimas 1 Subd., Pct. No. 1 reflecting a net decrease in the amount of $8,039.05 because residents installed concrete driveways after survey was completed that permitted less quantities of material as reflected through documentation by project engineer, TEDSI Infrastructure Group-CAP-08-033-03-31

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1311-431-121-865-1-731/733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

P.O.# 621821 for Valley Paving, Inc.

Obj. 733-Amount available as of 7-9-09 $9,335.05
Obj. 731-Amount available as of 7-9-09 $18,430.55

If Change Order gets approved by CC the contract price will decrease to $50,191.25.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/09/2009 10:38 AM
Budget and Management Erika Zamora 07/09/2009 10:46 AM
Auditor's Office 07/10/2009 05:07 PM
Form Started By:
mjackson
Started On:
07/08/2009 04:34 PM
Final Approval Date:
07/10/2009