CAPTION

Approval of Change Order No. 1 with contractor Closner Construction Co., LLC for Sundowner Recreational Center Subdivision, Pct. No. 2 reflecting a net increase in the amount of $6,678.00 because of (2) manholes, a 181 LF of Trench excavation Protection and a 75 LF of RC Pipe were added to project as submitted through project engineer DOS Logistics Inc. (Bid No. CAP 09-188-05-06-YSI, contract No. C-CAP-09-188-07-07).

BACKGROUND


Fiscal Impact

FISCAL YEAR:
9
ACCT. #:
9-1312-431-00-122-940-0-733/841
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

P.O.# 625663 available balance(s) are:

Obj.733 - 100,262.00
Obj.841 - 75,695.56

*Interlocal Agreement with City of San Juan will fund remaining cost of project.

CC Approval of change order#1 will increase the contract price to $226,675.65

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/15/2009 03:13 PM
Budget and Management Erika Zamora 07/15/2009 03:34 PM
Auditor's Office 07/17/2009 05:21 PM
Form Started By:
mjackson
Started On:
07/13/2009 04:45 PM
Final Approval Date:
07/17/2009