Acceptance and approval of Change Order No. 1 with contractor, Alvarez Construction, for El Charro Subdivision, Pct. No. 2 reflecting a net increase in the amount of $2,000.00 because curb inlets at Maya Street needed to be adjusted along with the street profile (6 extra days were requested by contractor) including Contractor's request for an additional (8) construction days due to rain and wet days as submitted through project engineer, R. Gutierrez Engineering Corporation-Contract No. C-CAP-09-001-04-21.
BACKGROUND
Contract Price with change order no.1 - $196,300.50
Fiscal Impact
- FISCAL YEAR:
- 9
- ACCT. #:
- 9-1311-431-00-122-240-1-733
- FUNDS AVAILABLE Y/N?:
- Y/pending
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds will be available pending LIT AI-16693 8/04/09.Ref: PO#622455
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 07/29/2009 01:59 PM |
| Budget and Management | Erika Zamora | 07/29/2009 02:19 PM |
| Auditor's Office | 07/31/2009 05:18 PM |
- Form Started By:
- mjackson
- Started On:
- 07/28/2009 10:12 AM
- Final Approval Date:
- 07/31/2009