1. Sharyland Water Supply Corporation:
a. A 6" PVC waterline to begin 40 ft. North of the centerline of the intersection of FM 1924 & Bentsen Palm Dr. then to go   North for a distance of approximately 3/4 mile.  Waterline to be located 5 ft. West of East R.O.W. line of Bentsen Palm Dr.

b. A 6" PVC waterline to begin 150 ft. North of the centerline of the intersection of Janie St. & Bentsen Palm Dr. then to go North for a distance of approximately 1/2 mile.  Waterline to be located 5 ft. West of East R.O.W. line of Bentsen Palm Dr.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Erika Zamora 10/21/2009 01:19 PM
Auditor's Office lfong 10/23/2009 03:46 PM
Form Started By:
Saul Garcia
Started On:
10/20/2009 08:26 AM
Final Approval Date:
10/23/2009