CAPTION

Presentation for consideration, discussion, acceptance and approval of Change Order No. 1 with contractor M Construction LTD for Jessan Subdivision, Pct. No. 3 reflecting an decrease in the amount of $6,156.87 because of Quantitative adjustments based on revision 1 as submitted through project engineer Hinojosa Engineering, Inc. (C-CAP-09-131-05-05)

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1XXX-431-00-123-350-0-73X
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Change Order will decrease P.O. #630176 in the amount of $6,156.87 leaving the P.O. with a balance of $40,626.15. Pending P.O. Increase of $639.13 for roads, refer to AI - 18662 (11/24/09 CC). Please refer to attached P.O. #630176.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/18/2009 12:08 PM
Budget and Management Erika Zamora 11/18/2009 01:21 PM
Auditor's Office Alejandro Garcia 11/19/2009 02:23 PM
Form Started By:
mjackson
Started On:
11/17/2009 09:06 AM
Final Approval Date:
11/19/2009