AI- 19331
14.I.
CC CONSENT
Meeting Date:
01/19/2010
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

Information

CAPTION

Acceptance and approval of Change Order No. 2 with contractor Closner Construction Co. for Sundowner Recreational Center Subdivision, Pct. No. 2 reflecting a request for contract time extension due to rain days, easement delay days and water line services adjustments delay days as submitted through project engineer DOS Logistics, Inc. (C-CAP-09-188-07-07)

BACKGROUND

29 days added to contract. Total calendar days : 149

Fiscal Impact

FISCAL YEAR:
9
ACCT. #:
9-1312-431-00-122-0-940-0-XXX
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Change order will not affect contract amount.
Reference PO#: 625663

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/14/2010 01:11 PM
Budget and Management Erika Zamora 01/14/2010 01:20 PM
Auditor's Office 01/15/2010 04:35 PM
Form Started By:
mjackson
Started On:
01/08/2010 11:13 AM
Final Approval Date:
01/15/2010