CAPTION
Hidalgo County Urban County Program is requesting acceptance and approval of Change Order No. 1 with contractor Garcia & Martinez Paving, Inc. for South Tower Estates Subdivision in Precinct No. 2. The request reflects a contract increase in the amount of $81,129.60 and a 45-day time extension due to additional construction as submitted through project engineer R. Gutierrez Engineering Corporation. CDBG-R funds are being expended for this project.
BACKGROUND
Precinct No. 2 is requesting additional quantities on eleven (11) items which will increase contract amount by 21.4% of original contract, $378,816.15.
Awarded Vendor: Garcia & Martinez Paving, Inc.
Revised Contract Amount: $459,990.75
Funds Available: $509,653.80 CDBG-R Flood Drain Improvements (B-09-UY-48-0501)
Awarded Vendor: Garcia & Martinez Paving, Inc.
Revised Contract Amount: $459,990.75
Funds Available: $509,653.80 CDBG-R Flood Drain Improvements (B-09-UY-48-0501)
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- Urban County Funds
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Urban County CDBG-R Flood Drain Improvements funds will be utilized for the increase of $80,816.35.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 03/10/2010 08:46 AM |
| Auditor's Office | 03/12/2010 05:29 PM |
- Form Started By:
- ewebber
- Started On:
- 03/10/2010 08:32 AM
- Final Approval Date:
- 03/12/2010