AI- 20320
21.B.2.
CC REGULAR
- Meeting Date:
- 03/16/2010
- Submitted For:
- Rocio Villarreal
- Submitted By:
- Rocio Villarreal, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Requesting approval of Supplemental Agreement No. 1 to Work Authorization No. 7 for current contract with Millennium Engineers Group, Inc for the "New Hidalgo County Precinct No. 2 Administrative Buildings," to reflect a $880.00 increase to the total project estimated cost, bringing the total estimated project cost to $40,736.50 C-08-316-10-28
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2010
- ACCT. #:
- 0-133X-4XX-00-122-0XX-0-720
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
0-1332-415-15-122-042-0-720 0-1334-431-00-122-021-0-7200-1334-441-00-122-041-0-720 0-1334-415-15-122-042-0-720
0-1336-412-00-122-043-0-720
available balances as of 03/12/10.
PO#631532 will need an increase of $880.00 Ref:AI-18180 CC 10/27/09 WA#7 approved
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/11/2010 11:06 AM |
| Budget and Management | Erika Zamora | 03/11/2010 02:30 PM |
| Auditor's Office | 03/12/2010 05:29 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 03/10/2010 04:20 PM
- Final Approval Date:
- 03/12/2010