CAPTION

Requesting approval of Supplemental Agreement No. 1 to Work Authorization No. 7 for current contract with Millennium Engineers Group, Inc for the "New Hidalgo County Precinct No. 2 Administrative Buildings," to reflect a $880.00 increase to the total project estimated cost, bringing the total estimated project cost to $40,736.50 C-08-316-10-28

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2010
ACCT. #:
0-133X-4XX-00-122-0XX-0-720
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

0-1332-415-15-122-042-0-720 0-1334-431-00-122-021-0-720
0-1334-441-00-122-041-0-720 0-1334-415-15-122-042-0-720
0-1336-412-00-122-043-0-720
available balances as of 03/12/10.

PO#631532 will need an increase of $880.00 Ref:AI-18180 CC 10/27/09 WA#7 approved

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 03/11/2010 11:06 AM
Budget and Management Erika Zamora 03/11/2010 02:30 PM
Auditor's Office 03/12/2010 05:29 PM
Form Started By:
Rocio Villarreal
Started On:
03/10/2010 04:20 PM
Final Approval Date: