AI- 20746
21.C.3.
CC REGULAR
- Meeting Date:
- 04/20/2010
- Submitted For:
- Nielda Cavazos
- Submitted By:
- Nielda Cavazos, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
a. Requesting exemption from competitive bidding requirements under the Texas Local Government Code, Section 262.024 (A) (4) a professional service/Review Appraisal Services;
b. Presentation of scoring grid (for the purposes of ranking by CC) of the firms graded & evaluated through the County's approved "pool" of engineers in connection with professional Review Appraisal Services with TxDot ROWIS A-10 forms required for Hidalgo County Pct. # 4 "San Carlos Drainage Improvement Project"on an "as Needed Basis" for the duration of the project.
1st._________________;2nd._________________;3rd. ______________
c. Authority for the Purchasing Department to negotiate a professional Review Appraisal Services Contract with the No.1 ranked firm of ___________________________ for the provision of Review Appraisal Services for Hidalgo County Pct. 4 San Carlos Drainage Improvement Project.
b. Presentation of scoring grid (for the purposes of ranking by CC) of the firms graded & evaluated through the County's approved "pool" of engineers in connection with professional Review Appraisal Services with TxDot ROWIS A-10 forms required for Hidalgo County Pct. # 4 "San Carlos Drainage Improvement Project"on an "as Needed Basis" for the duration of the project.
1st._________________;2nd._________________;3rd. ______________
c. Authority for the Purchasing Department to negotiate a professional Review Appraisal Services Contract with the No.1 ranked firm of ___________________________ for the provision of Review Appraisal Services for Hidalgo County Pct. 4 San Carlos Drainage Improvement Project.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding will be identified at a later dateAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 04/14/2010 04:08 PM |
| Budget and Management | Erika Zamora | 04/14/2010 04:24 PM |
| Auditor's Office | 04/16/2010 05:29 PM |
- Form Started By:
- ncavazos
- Started On:
- 04/12/2010 01:55 PM
- Final Approval Date:
- 04/16/2010