Skip to main content

AgendaQuick™

View Agenda Item

AI- 22305
20.C.1.
CC REGULAR
Meeting Date:
08/10/2010
Submitted For:
Yolanda Cisneros
Submitted By:
Yolanda Cisneros, COMM. PCT. #2
Department:
COMM. PCT. #2

CAPTION

Acceptance and approval of Work Authorization No.8 with Millennium Engineers Group, Inc., Contract #C-09-485-01-12 for Construction Materials Engineering Services for the Alamo Road Crossing Drainage Improvement Project.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2010
ACCT. #:
0-1339-431-00-122-039-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funding available in the amount of $309,974.33 as of 08/06/2010.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/05/2010 01:47 PM
Budget and Management Erika Zamora 08/05/2010 01:57 PM
Auditor's Office 08/06/2010 05:21 PM
Form Started By:
ycisneros
Started On:
08/03/2010 02:05 PM
Final Approval Date: