CAPTION
A. Request approval of Change Order No. 6 on the Contract with Longhorn Excavators, Inc. for the Construction of Mission Levee Improvement Project-Inspiration Rd. to Abram Rd. (3.91 miles).
B. Request approval of Change Order No. 18A and No. 28 on the Contract with Ballenger Construction Company for the Construction of Levee DHS 0-4A. Subject to Department of Homeland Security (DHS) concurrence.
C. Request approval of Change Order No. 10, No. 11, No. 13 and No. 14 on the Contract with Ballenger Construction Company for the Construction of Levee DHS 0-4C. Subject to Department of Homeland Security (DHS) concurrence.
D. Request approval of Change Order No. 29 on the Contract with SER Construction Partners, LTD. for the Construction of Levee DHS 0-7. Subject to Department of Homeland Security (DHS) concurrence.
E. Request approval of Change Order No. 21 on the Contract with Williams Brothers Construction Co., Inc. for the Construction of Levee DHS 0-9 PH I. Subject to Department of Homeland Security (DHS) concurrence.
F. Request approval of Change Order No. 22 on the Contract with Williams Brothers Construction Co., Inc. for the Construction of Levee DHS 0-10. Subject to Department of Homeland Security (DHS) concurrence.
B. Request approval of Change Order No. 18A and No. 28 on the Contract with Ballenger Construction Company for the Construction of Levee DHS 0-4A. Subject to Department of Homeland Security (DHS) concurrence.
C. Request approval of Change Order No. 10, No. 11, No. 13 and No. 14 on the Contract with Ballenger Construction Company for the Construction of Levee DHS 0-4C. Subject to Department of Homeland Security (DHS) concurrence.
D. Request approval of Change Order No. 29 on the Contract with SER Construction Partners, LTD. for the Construction of Levee DHS 0-7. Subject to Department of Homeland Security (DHS) concurrence.
E. Request approval of Change Order No. 21 on the Contract with Williams Brothers Construction Co., Inc. for the Construction of Levee DHS 0-9 PH I. Subject to Department of Homeland Security (DHS) concurrence.
F. Request approval of Change Order No. 22 on the Contract with Williams Brothers Construction Co., Inc. for the Construction of Levee DHS 0-10. Subject to Department of Homeland Security (DHS) concurrence.
BACKGROUND
Fiscal Impact
Attachments
- Mission Levee CO#6
- DHS 0-4A CO#18A
- DHS 0-4A CO#28
- DHS 0-4C CO#10
- DHS 0-4C CO#11
- DHS 0-4C CO#13
- DHS 0-4C CO#14
- DHS 0-7 CO#29
- DHS 0-9 PH I CO#21
- DHS 0-10 CO#22
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Erika Zamora | 08/13/2010 01:39 PM |
| Final Approval | 08/13/2010 04:28 PM |
- Form Started By:
- mluna
- Started On:
- 08/13/2010 10:07 AM
- Final Approval Date:
- 08/13/2010