a. Status report submitted by Richard Sunday, Facilities Management, on the current on-going renovations to the third floor of the Adm. Bldg. including, but not limited to, specific preparation/necessary projects requiring completion prior to commencement of general contractor renovations, described as:
1. Asbestos Abatement through awarded vendor - R.L. Abatement, Inc.;
2. Elevator Modernization Project through awarded vendor - Thyssen Krupp;
3. Fire Alarm System Repair Project through awarded vendor - Firetrol;
b. Status report by project architect, Alcocer/Garcia Associates, Inc. on the (Renovation of first and second floors-including South wing of Adm. Bldg. - 100 E. Cano, Edinburg, TX) plans and specifications of the project and discussions/meeting with Judge-elect on review of County Judge office areas with applicable action/approval including, but not limited to the following:
1. Proposed date to submit final plans/specifications for CC approval; and, thereafter,
2. Proceed to advertise the project with the approved plans/specifications;
3. Submission of timelines for project;
4. Other related issues
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- various
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
2006-2010 C/O proceeds would be used for renovations to Adm. Bldg., 100 E. CANO, Edinburg, TXSee attached for the expense reports for the various accounts as of 10/01/10.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | 10/08/2010 03:57 PM |
- Form Started By:
- Alejandro Garcia
- Started On:
- 10/06/2010 04:12 PM
- Final Approval Date:
- 10/08/2010