CAPTION
Requesting approval of Change Order No. 2 (decrease) in the amount of $3,860.44 with Leal Construction, Inc. (contracted vendor for "Alamo road Crossing Drainage Improvement Project") reflecting the following changes:
a. No Temporary Asphalt Section for Traffic Control Plan used.;
b. 24 LF of 72" RCP-RJ CL III Storm Drain Pipe (material only);
c. 121 LF of 72" RCP-RJ CL III Storm Drain Pipe used instead of 145 LF.;
d. 121 LF of Gravel Bedding used instead of 145 LF.; and,
e. Additional 117 SY of Concrete Rip Rap used,
with authority for County Judge or Court Member to execute document.
BACKGROUND
Contract #C-10-178-06-22 PO #643847
Fiscal Impact
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1342-431-00-122-039-1-XXX
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Revised contract amount will be $178,487.54 after CO#2.
Current PO amount is $182,347.98
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/24/2011 03:47 PM |
| Budget and Management | Erika Zamora | 03/24/2011 03:51 PM |
| Auditor's Office | 03/31/2011 04:00 PM |
- Form Started By:
- ycisneros
- Started On:
- 03/24/2011 01:32 PM
- Final Approval Date:
- 03/31/2011