CAPTION

Requesting approval of Change Order No. 2 (decrease) in the amount of $3,860.44 with Leal Construction, Inc. (contracted vendor for "Alamo road Crossing Drainage Improvement Project") reflecting the following changes:

a. No Temporary Asphalt Section for Traffic Control Plan used.;
b. 24 LF of 72" RCP-RJ CL III Storm Drain Pipe (material only);
c. 121 LF of 72" RCP-RJ CL III Storm Drain Pipe used instead of 145 LF.;
d. 121 LF of Gravel Bedding used instead of 145 LF.; and,
e. Additional 117 SY of Concrete Rip Rap used,

with authority for County Judge or Court Member to execute document.

BACKGROUND

Contract #C-10-178-06-22 PO #643847

Fiscal Impact

FISCAL YEAR:
2011
ACCT. #:
1-1342-431-00-122-039-1-XXX
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Revised contract amount will be $178,487.54 after CO#2.
Current PO amount is $182,347.98

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 03/24/2011 03:47 PM
Budget and Management Erika Zamora 03/24/2011 03:51 PM
Auditor's Office 03/31/2011 04:00 PM
Form Started By:
ycisneros
Started On:
03/24/2011 01:32 PM
Final Approval Date:
03/31/2011