CAPTION
Urban County Program is requesting consideration and action to award and enter into a Construction Contract with Tropical Contracting, LLC in the amount of $916,512.02 for the Pct. 1 Delta Outfall Drainage Improvements Project.
BACKGROUND
The bid opening was held March 30, 2011 and the bidder meeting all specifications and/or requirements is Tropical Contracting, LLC. The project involves drainage structure improvements for the Delta Area Outfall System. Please see attached recommendation by the project engineer (Dos Logistics, Inc.).
Contractor: Tropical Contracting, LLC.
Contract Amount: $916,512.02
Funds Available: $1,072,112.00
Contractor: Tropical Contracting, LLC.
Contract Amount: $916,512.02
Funds Available: $1,072,112.00
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- Urban County Funds
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Urban County funds will be utilized for the drainage structure improvements for the Delta Area Outfall System.Contract Amount: $ 916,512.02
Available Funds: $1,072,112.00
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Alejandro Garcia | 03/31/2011 07:02 AM |
| Auditor's Office | 03/31/2011 04:00 PM |
- Form Started By:
- ewebber
- Started On:
- 03/30/2011 03:38 PM
- Final Approval Date:
- 03/31/2011