AI- 26477
5.A.
CC CONSENT
- Meeting Date:
- 05/10/2011
- Submitted For:
- Joe Pena
- Submitted By:
- Sandra Garcia, RIGHT OF WAY DEPT.
- Department:
Information
CAPTION
1. North Alamo Water Supply:
a. Approximately 500' going east from the centerline of mile 6W and 15N on the east side of Barrera St-Bore-Juan R. Benavides- 3/4" service connection
2. City of Mission:
a. Proposed 8" PVC sewermain line parallel to and 5 feet inside the East R.O.W. line of Glasscock Road. Beginning at a distance 3730 feet of South of Mile 5 Road and continuing South along said alignment a distance of 1564 feet. The proposed sewer line will be bored where it crosses Minnesota Road.
a. Approximately 500' going east from the centerline of mile 6W and 15N on the east side of Barrera St-Bore-Juan R. Benavides- 3/4" service connection
2. City of Mission:
a. Proposed 8" PVC sewermain line parallel to and 5 feet inside the East R.O.W. line of Glasscock Road. Beginning at a distance 3730 feet of South of Mile 5 Road and continuing South along said alignment a distance of 1564 feet. The proposed sewer line will be bored where it crosses Minnesota Road.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Alejandro Garcia | 05/04/2011 03:34 PM |
| Auditor's Office | 05/06/2011 04:49 PM |
- Form Started By:
- Saul Garcia
- Started On:
- 05/03/2011 04:51 PM
- Final Approval Date:
- 05/06/2011