Seeking approval of Change Order No. 1 with contractor M. J. A. Construction, LLC for Colonia Saenz Subdivision, Pct. No. 1 reflecting a net increase of $1,691.00 due to addition of grated inlet and RCP as submitted through project engineer Rodriguez Engineering (C-CAP-11-057-04-05).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1312-431-00-121-181-0-73X
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Req #199737 for M. J. A. Construction, LLC in relation to Colonia SaenzObj. 733 "Drainage Ditches" - Amount available as of 7-27-11 $14,509.00 ; Available balance on acct is $1,691.00 to cover Change Order #1. A PO increase to reflect the Change Order increase will be processed after CC approval
Obj. 731 "Roads" - Amount available as of 7-27-11 $46,287.83
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1200-431-00-121-181-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Req #199737 for M. J. A. Construction - Amount available as of 7-28-11 $2,352.67Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 07/27/2011 03:23 PM |
| Auditor's Office | Alejandro Garcia | 07/29/2011 05:01 PM |
- Form Started By:
- mjackson
- Started On:
- 07/27/2011 02:53 PM
- Final Approval Date:
- 07/29/2011