CAPTION
The Urban County Program is requesting approval of a best and final negotiated contract with Guzman & Munoz Engineering & Surveying, Inc. in the amount of $14,200.00 utilizing Years 19, 20 & 22 (2006, 2007 & 2009) Hidalgo County Precinct No. 1 (Edcouch) funds for professional engineering services for the Water/Sewer Improvements at the Edcouch Water Treatment Plant.
BACKGROUND
Guzman & Munoz Engineering & Surveying, Inc. has submitted a best and final offer for professional engineering services for the Water/Sewer Improvements at the Edcouch Water Treatment Plant located within the Hidalgo County Precinct No. 1 boundaries. Guzman & Munoz Engineering & Surveying, Inc., was the highest rated firm by Commissioners' Court. Contract approval in the amount of $14,200.00 is being requested. See attached scope of services and copy of proposed contract.
Contract Amount: $ 14,200.00
Funds Available: $ 14,758.53 (FY 19-2006), $11,119.19 (FY 20- 2007) & $43,461.60 (FY 22-2009)
Precinct No. 1 (Edcouch) Water/Sewer Improvement funds.
Contract Amount: $ 14,200.00
Funds Available: $ 14,758.53 (FY 19-2006), $11,119.19 (FY 20- 2007) & $43,461.60 (FY 22-2009)
Precinct No. 1 (Edcouch) Water/Sewer Improvement funds.
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- Urban County Funds
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Urban County Year 19 (2006), Year 20 (2007) & Year 22 (2009) funds will be utilized for the water/sewer Improvements at the Edcouch Water Treatment Plant.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 08/16/2011 04:58 PM |
| Auditor's Office | aduran | 08/17/2011 01:31 PM |
| Purchasing / Internal | msalazar | 08/17/2011 03:37 PM |
- Form Started By:
- ewebber
- Started On:
- 08/16/2011 04:46 PM
- Final Approval Date:
- 08/17/2011