AI- 29820
7.C.
CC CONSENT
- Meeting Date:
- 11/29/2011
- Submitted For:
- Yoli Cisneros
- Submitted By:
- Yolanda Cisneros, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Requesting approval of Construction Change Order No. 1 an increase in the amount of $17,000.00 with Mission Paving Company, Inc. (contracted vendor for “Tower Road-Phase I Rd. & Drainage Project”) reflecting the changes detailed on the change order request with authority for County Judge to execute document.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2011
- ACCT. #:
- 1-1200-431-00-122-049-0-731
- FUNDS AVAILABLE Y/N?:
- y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO #662859Funding available in the amount of $90,855.25 as of 11/22/2011.
See attached PO Increase
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/22/2011 02:21 PM |
| Budget and Management | mmunoz | 11/22/2011 02:53 PM |
| Auditor's Office | Alejandro Garcia | 11/23/2011 01:39 PM |
- Form Started By:
- ycisneros
- Started On:
- 11/22/2011 11:43 AM
- Final Approval Date:
- 11/23/2011