4.
DRAINAGE DISTRICT
- Meeting Date:
- 05/29/2012
- Submitted By:
- Jaime Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A.) Requesting approval to issue purchase order to Skyline Steel for the purchase of sheet pile. As it relates to the Declaration of Emergency previously approved by the Hidalgo County Drainage District No.1 Board of Directors on April 10, 2012, Agenda Item-31762 items A & E. Reconstruction of the Weir Structure on the Main Flood Water Channel.
B.) Requesting approval to advertise for the following:
1.) RFB No. 12-011-07-11 Hidalgo County Drainage District No.1-"J-09 Drain Improvements-Phase I Irrigation Siphons".
C.) Presentation of scoring grid of the firms evaluated through the District's "Pool" of Professional Engineers for the purpose of ranking by the Hidalgo County Drainage District No.1 Board of Directors. As it relates to the Updating of the Hidalgo County Drainage Master Plan and Development Drainage Improvements for the Hidalgo County Drainage District No1. within Pct. 3.
B.) Requesting approval to advertise for the following:
1.) RFB No. 12-011-07-11 Hidalgo County Drainage District No.1-"J-09 Drain Improvements-Phase I Irrigation Siphons".
C.) Presentation of scoring grid of the firms evaluated through the District's "Pool" of Professional Engineers for the purpose of ranking by the Hidalgo County Drainage District No.1 Board of Directors. As it relates to the Updating of the Hidalgo County Drainage Master Plan and Development Drainage Improvements for the Hidalgo County Drainage District No1. within Pct. 3.
| FIRM NAME | SCORE | RANK |
| L&G ENGINEERING | 100 | |
| JAVIER HINOJOSA ENGINEERING | 91 | |
| QUINTANILLA HEADLEY & ASSOCIATES | 88 |
D.) Pursuant to the Boards approval, requesting authority for Hidalgo County Drainage District No.1 to negotiate contract with the number one ranked firm of __________________________________________ for Professional Engineering Services-Updating of the Hidalgo County Drainage Master Plan and Development Drainage Improvements for the Hidalgo County Drainage District No1. within Pct. 3.
E.) Presentation of scoring grid of the firms evaluated through the District's "Pool" of Professional Engineers for the purpose of ranking by the Hidalgo County Drainage District No.1 Board of Directors. As it relates to the Updating of the Hidalgo County Drainage Master Plan and Development Drainage Improvements for the Hidalgo County Drainage District No1. within Pct. 2.
| FIRM NAME | SCORE | RANK |
| R. GUTIERREZ ENGINEERING CORP. | 95 | |
| QUINTANILLA HEADLEY & ASSOCIATES | 87 | |
| JAVIER HINOJOSA ENGINEERING | 85 |
F.) Pursuant to the Boards approval, requesting authority for Hidalgo County Drainage District No.1 to negotiate contract with the number one ranked firm of __________________________________________ for Professional Engineering Services-Updating of the Hidalgo County Drainage Master Plan and Development Drainage Improvements for the Hidalgo County Drainage District No1. within Pct. 2.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 05/24/2012 11:50 AM |
| Final Approval | Monica Salinas | 05/25/2012 10:03 AM |
- Form Started By:
- Jaime Salazar
- Started On:
- 05/24/2012 09:05 AM
- Final Approval Date:
- 05/25/2012