AI- 32945
Precinct #2 14.A.
CC REGULAR
- Meeting Date:
- 06/26/2012
- Submitted By:
- Katia Garcia, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Presentation for consideration, discussion, acceptance and approval of the following with Saenz Utility Contractors, Ltd. for El Dora Road & Drainage Improvements Project, as submitted and recommended by project engineer R. Sesin;
a. Certificate of Substantial Completion
b. Application for Retainage in the amount of $19,433.68
c. Certificate of Construction Completion reflecting completion date of March 12, 2012
with authority for County Judge or Court member to execute documents
a. Certificate of Substantial Completion
b. Application for Retainage in the amount of $19,433.68
c. Certificate of Construction Completion reflecting completion date of March 12, 2012
with authority for County Judge or Court member to execute documents
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2012
- ACCT. #:
- 2-1200-206-00-122-023-0-000
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Available balance $18,273.68 pending retainage for Application for Payment #3
Attachments
- Certificate of Substantial Completion
- Certificate of Construction Completion
- Application for Retainage
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 06/21/2012 03:23 PM |
| Purchasing / Internal | Monica Salinas | 06/22/2012 04:26 PM |
- Form Started By:
- Katia Garcia
- Started On:
- 06/21/2012 01:23 PM
- Final Approval Date:
- 06/22/2012