CAPTION
Seeking approval of Change Order No. 2 with contractor Saenz Utility Contractors, Ltd. for Munoz Subdivision, Pct. No. 3 reflecting a reconciliation of quantities resulting in a decrease of $25,716.85 as submitted through project engineer Javier Hinojosa Engineering (C-CAP-12-019-01-31).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2012
- ACCT. #:
- 2-1312-431-00-123-488-0-731/733
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available funds in P.O. #674557 as of 10/26/12 are $213,200.40. There is a decrease of $36,679.15 in Roadway Items (731) and an increase of $10,962.30 in Drainage Items (733). Available funds in Obj Code 733 are $130,743.70.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 10/25/2012 12:48 PM |
| Budget and Management | mmunoz | 10/25/2012 12:54 PM |
| Auditor's Office | Alejandro Garcia | 10/26/2012 10:29 AM |
- Form Started By:
- mjackson
- Started On:
- 10/23/2012 11:00 AM
- Final Approval Date:
- 10/26/2012