AI- 35136
Purchasing Department 19.E.1.
CC REGULAR
- Meeting Date:
- 11/13/2012
- Submitted For:
- Marty Salazar
- Submitted By:
- Moises Salazar, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Acceptance and approval of the Final AIA Document A101 form of Agreement between Hidalgo County-Owner and HighMark Construction, LLC, awarded contractor in the amount of $465K for the project: Hidalgo County "Additions and Renovations to the WIC Clinic/Offices located at 3105 E. Richardson, Edinburg, TX"-C-12-021A-09-25.
BACKGROUND
Award Date: 09/25/12 (AI No. 34372)
Project Amount: $465,000.00
AIA Agreement has been approved as to form by Legal Counsel
Project Amount: $465,000.00
AIA Agreement has been approved as to form by Legal Counsel
Fiscal Impact
- FISCAL YEAR:
- 2012
- ACCT. #:
- 2-1292-441-0-350-001-2-720
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding available through PO#681804 in the amount of $465,000.00 as of 11/9/12 for Highmark Construction Co. LLC.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/08/2012 04:54 PM |
| Budget and Management | mmunoz | 11/09/2012 08:23 AM |
| Auditor's Office | Alejandro Garcia | 11/09/2012 03:46 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/06/2012 03:08 PM
- Final Approval Date:
- 11/09/2012