AI- 39990
Purchasing Department 13.A.
CC CONSENT
- Meeting Date:
- 08/27/2013
- Submitted For:
- Raul Silguero
- Submitted By:
- Carlos Jasso, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Presentation for consideration, discussion, acceptance and approval of following with REIM Construction, Inc. for Minnesota Road West "I" Road project, as submitted and recommended by project engineer, Raul Sesin, contract # C-12-273-12-28:
1. Application for Final Payment in the amount of $
2. Application for Retainage in the amount of $
3. Certificate of Construction Completion reflecting the completion date of May 2, 2013.
1. Application for Final Payment in the amount of $
2. Application for Retainage in the amount of $
3. Certificate of Construction Completion reflecting the completion date of May 2, 2013.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2013
- ACCT. #:
- 3-1200-431-00-122-084-0-731/841
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Available funds in P.O#689764 as of 7/31/2013(731) County will pay 33% of cost and (841) City will pay 67% of cost.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Auditor's Office | Monica Salinas | 08/23/2013 05:16 PM |
- Form Started By:
- Clarissa Jasso
- Started On:
- 07/31/2013 04:24 PM
- Final Approval Date:
- 08/23/2013