- Meeting Date:
- 06/05/2007
- Submitted For:
- Rocio Villarreal
- Submitted By:
- Rocio Villarreal, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
A. Requesting approval of Change Order No.6 (Fire Sprinkler Check Valve) in connection with the "Hidalgo County Administration Building" in the amount of $1,278.00 (Repair Allowance from contracted vendor, Joe Williamson Construction Co., and as recommended by project architect,Rike Ogden Figueroa Allex Architects , with authority for County Judge to execute document. C-06-092-07-25;
B. Requesting approval of revised/amend Change Order No.2 (approved by CC on 3/21/07) in connection with the "Hidalgo County Administration Building" to reflect amount to be deducted from Allowance Repair submitted from Descon Construction LP, and as recommended by project architect, ROFA Architects with authority for County Judge or Presiding Com. Court Officer to execute.
C. Approval of correction of Change Order Number (as approved by CC on 5/29/07 as Change Order no. 4) to Change Order No. 5 in connection with the "Hidalgo County Administration Building."
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2007
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
No budgetary impact to the county. Funding is to come from the internal project contingency allowance.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 05/30/2007 05:26 PM |
| Budget and Management | Dina Trevino | 05/31/2007 11:07 AM |
| Auditor's Office | lfong | 06/01/2007 09:03 AM |
| Court Administrator | Monica Salinas | 06/01/2007 09:34 AM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 05/30/2007 09:10 AM
- Final Approval Date:
- 06/01/2007