AI- 41043
Purchasing Department 7.C.
CC CONSENT
- Meeting Date:
- 10/07/2013
- Submitted For:
- Raul Silguero
- Submitted By:
- Carlos Jasso, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Acceptance and approval of Change Order No.2 reflecting a decrease of $80.00 to delete two (2) unused inlet storm water protection with contractor 2GS, L.L.C. for the Pct. 2 McColl Road Overlay Curb & Gutter Improvements, as submitted through project engineer Raul Sesin (C-13-139-05-21).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2013
- ACCT. #:
- 3-1200-431-00-122-087-0-841
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | dbetancourt | 10/03/2013 05:09 PM |
| Auditor's Office | Monica Salinas | 10/03/2013 05:49 PM |
- Form Started By:
- Clarissa Jasso
- Started On:
- 10/02/2013 09:10 AM
- Final Approval Date:
- 10/03/2013