AI- 44086
Purchasing Department   8.E.
CC CONSENT
Meeting Date:
04/22/2014
Submitted For:
Comm. Tito Palacios, Pct. #2
Submitted By:
Erika Zamora, COMM. PCT. #2
Department:
COMM. PCT. #2

Information

CAPTION

Requesting approval of Change Order No. 1 reflecting an increase of +$8,125.84-four additional driveways and an additional 28 working days with Contractor RDH Site and Concrete Co. for Pct 2 Rancho Blanco Road Project, as submitted through project engineer,  R. Gutierrez Engineering Corp (C-13-250-01-14).

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2014
ACCT. #:
4-1200-431-00-122-086-0-731
FUNDS AVAILABLE Y/N?:
Y/Pending
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funds pending interdepartmental transfer on the agenda for approval on 4/22/14 AI#44093.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/16/2014 01:32 PM
Budget and Management Debbie Tamez 04/16/2014 01:36 PM
Auditor's Office Monica Salinas 04/17/2014 02:24 PM
Form Started By:
Erika Zamora
Started On:
04/14/2014 10:29 AM
Final Approval Date:
04/17/2014