AI - 45504
7.
DRAINAGE DISTRICT
- Meeting Date:
- 07/15/2014
- Submitted For:
- Lora Briones
- Submitted By:
- Lora Briones, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A. 2013 Bond Series - Construction Projects.
1. Request approval of Payment application #1 for Texas Cordia Construction, LLC in the amount of $62,689.50 pertaining to the construction of PCT 4 Edinburg Drain Stub- Out to South Main Drain Control Structure Project
2. Request approval of Payment application #1 to GP7 Construction, Inc. in the amount of $42,611.30. Construction is for the FM 495 Drain - Trenton Road Field Crossing.
3. Request approval of Final Payment Application and the release of retainage in the amount $ 91,304.30 to Rojas Construction and Paving, LLC for the Construction of PCT 2 RDD- North side Village and Hidden Valley Sub Area Drainage Improvements.
B. Maintenance and Operation Projects - General Fund
1. Request approval of Payment Request #6 from Texas Cordia Construction LLC in the amount of $5,914.17 for the Construction of the Alamo Expressway Drainage Crossing
2,. Request approval of Payment Application #3 to Texas Cordia Construction, LLC in the amount of $225,785.70 for the Construction of the Edinburg WWTP Effluent Line and Crossing.
1. Request approval of Payment application #1 for Texas Cordia Construction, LLC in the amount of $62,689.50 pertaining to the construction of PCT 4 Edinburg Drain Stub- Out to South Main Drain Control Structure Project
2. Request approval of Payment application #1 to GP7 Construction, Inc. in the amount of $42,611.30. Construction is for the FM 495 Drain - Trenton Road Field Crossing.
3. Request approval of Final Payment Application and the release of retainage in the amount $ 91,304.30 to Rojas Construction and Paving, LLC for the Construction of PCT 2 RDD- North side Village and Hidden Valley Sub Area Drainage Improvements.
B. Maintenance and Operation Projects - General Fund
1. Request approval of Payment Request #6 from Texas Cordia Construction LLC in the amount of $5,914.17 for the Construction of the Alamo Expressway Drainage Crossing
2,. Request approval of Payment Application #3 to Texas Cordia Construction, LLC in the amount of $225,785.70 for the Construction of the Edinburg WWTP Effluent Line and Crossing.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 07/14/2014 09:01 AM |
| Final Approval | Monica Salinas | 07/14/2014 10:25 AM |
- Form Started By:
- Lora Briones
- Started On:
- 07/11/2014 04:43 PM
- Final Approval Date:
- 07/14/2014